Projects / Pharmaceutical Manufacturing Facility

Pharmaceutical Manufacturing Facility

Contracted for the installation of two Purified Water (PUW) skids and a steam heat exchanger within an existing manufacturing facility. The works included the integration of the new systems with existing process and utility services to support pharmaceutical manufacturing operations. Rockwell delivered the project as the Project Supervisor Construction Stage (PSCS) and maintained the onsite safety, management of contractor interfaces, and ensured compliance with statutory health and safety requirements throughout the construction phase.

Scope

  • Installation of steam heat exchanger
  • Installation of two Purified Water (PUW) skids
  • Connection to existing steam, condensate, Chilled Water, Potable Water, H2 Vent and drainage services
  • Equipment installation
  • PSCS duties onsite, including safety coordination, inspections, and contractor management

Let’s Talk

See our contact page for further details, or fill out this form, and we’ll get back to you promptly.

"*" indicates required fields

Name*
This field is for validation purposes and should be left unchanged.
*Required Field.